Retail Distribution
Scope & Role
- 1.6M sq ft greenfield distribution center in the Midwest
- $125M capital budget
- Automation-rich design - AS/RS, goods-to-person, robotics, high-density racking
- Don Cooper served as Project Lead, responsible for construction, material handling equipment, and automation
Challenges
- Aggressive timeline for occupancy and go-live
- Integration of multiple automation vendors drove dense, complex building design
- Budget control under Covid-19 supply disruptions
Approach / Solution
- Directed a phased project plan with clear critical path controls
- Met with labor unions' leadership to garner support for a constructive partnership
- Coordinated automation, construction, and permitting streams to stay on schedule
- Performed multiple structural design reviews to maintain alignment on capacity
- Maintained tight cost controls and vendor accountability throughout design and build
Outcome / Impact
- Completed one month ahead of schedule
- Delivered 2% under budget on a $125M project
- Facility launched with full automation and throughput capacity
Turning complexity into capacity - this project delivered a flagship distribution center that sets the benchmark for a major retailer's future growth.
Client / Sector
Confidential - California Multi-shift Distribution Center
Scope & Role
- Installation/Retrofit of HVAC system in a 5x24 operating distribution center
- $16M capital budget
- Don Cooper served as Project Lead, directing strategy, design, and phased execution
Challenges
- Live facility with no option for contractor interior access Monday-Friday
- Rising employee turnover tied to extreme heat conditions
- State regulations tightening heat exposure regulations required action
Approach / Solution
- Structured work phases: exterior work on weekdays, interior installations completed on weekends
- Evaluated the potential HVAC designs to include not only cost but especially time to completion
- Selected air rotation units (ARUs) over rooftop units (RTUs) to achieve a better schedule and cost
- Coordinated closely with building inspectors to ensure full compliance with energy regulations
- Maintained 24/7 service levels while construction was underway
Outcome / Impact
- Completed two months ahead of schedule
- Delivered 6% under budget on a $16M project
- Achieved compliance with new heat exposure regulations
- Improved employee retention and working conditions
Compliance and performance can go hand in hand - turning a regulatory burden into a quality-of-workspace advantage.
Client / Sector
Distribution Center Infrastructure (South Carolina)
Scope & Role
- $7M infrastructure project, partially county-funded but primarily led and financed by Harbor Freight Tools
- Three-year duration, including county approvals and construction delivery
- Scope included highway widening, new traffic light, roadway demolition, connector roads, and improved turning radius
- Don Cooper served as Project Liaison and Design Contributor, aligning county, corporate, and site leadership with contractors and engineers
Challenges
- Site congestion plagued workforce and management for over two years, with long egress delays for 1,000+ associates
- Required coordination between county government, engineering firms, contractors, and corporate leadership
- Balancing cost-sharing and funding approvals with county and company stakeholders
Approach / Solution
- Assisted in roadway design and overall traffic flow planning
- Secured funding support from both Harbor Freight and county resources
- Acted as liaison across stakeholders: county, corporate, site leadership, engineers, and contractors
- Oversaw design reviews and ensured alignment with workforce and construction needs
- Supported demolition, road extension, connector design, and improved traffic flow into the DC campus
Outcome / Impact
- Completed successfully with widened South Carolina Hwy. 34 (from 3 lanes to 5 lanes)
- New traffic light on Hwy. 34 installed
- Connector and extension roads completed, improving access to employee parking and logistics flows
- Traffic congestion eliminated, dramatically improving safety and reducing wait times for 1,000 associates
- Strong example of public–private partnership that addressed workforce needs and regional infrastructure challenges
This project turned years of daily frustration into reliable access and safe traffic flow — strengthening both operations and workforce satisfaction.